OPA affirms Executive Director's decision not to award contract to Solid Builders
(April 23, 2004)
In its latest decision, OPA affirms the decision of the Executive Director not to award the contract to Solid Builders based on the deficiency in the bid security provided and denies Solid Builders’ appeal.
Based on its analysis of the appeal, OPA finds:
- Bid security is mandatory under CUC-PR §4-101(2) for construction procurement;
- Rejection of a bid for failure to provide bid security is mandatory under CUC-PR
§4-101(2)(c); - Solid Builders did not provide acceptable bid security;
- CUC properly rejected Solid Builders bid under CUC-PR §4-101(2)(c);
- Solid Builders is ineligible for award under the IFB.